COTABATO LIGHT & POWER COMPANY
ERC CASE NO. 2001-898 AND 2001-503
RATE PROFILE

Unit Residential Gen. Retail Service 1 (<=20KW) Gen. Retail Service 2 (>=20KW &<=40KW) Gen. Retail Service 3 (>=40KW &<=200KW) Gen. Retail Service 4 (>200KW) Flat Lighting Service
Generation Charge PhP/kWh 3.9943 3.9943 3.9943 3.9943 3.9943 3.9943
Power Act Reduction % 75.10%
Transmission Charge PhP/kWh 0.5255 0.5564 0.5179 0.4943 0.4423 0.6136
PhP/kW 243.0324 146.1457 163.3083
System Loss Charge PhP/kWh 0.3606 0.3642 0.4672 0.4179 0.3989 0.3701
Senior Citizen Subsidy PhP/kWh 1.9002 1.9002 0.3193 0.2748 0.0000 2.0783
PhP/kW 362.12 291.08 345.77
Supply Charge PhP/Cust/Mo. 138.97 285.92 2,008.16 78.96
PhP/kWh 0.1802 0.1802
Metering Charge PhP/Meter/Mo. 5.00 5.00 237.39 338.21 4,540.26
PhP/kWh 0.4573 0.4573
Fuel Recovery Charge PhP/kWh - - - - - -
Fuel Recovery ERC Case#2011-068RC PhP/kWh 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Automatic Fuel Recovery PhP/kWh 0.0117 0.0117 0.0117 0.0117 0.0117 0.0117
Lifeline Rate Subsidy PhP/kWh 0.0745 0.0745 0.0745 0.0745 0.0745 0.0745
Senior Citizen Subsidy PhP/kWh 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004
Inter-Class Cross Subsidies PhP/kWh - - - - - -
Surcharge % 2% 2% 2% 2% 2% 2%
Franchise Tax % 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%
VAT Rates
Generation Charge P/kWh 0.3005 0.3005 0.3005 0.3005 0.3005 0.3005
Transmission Charge P/kWh 0.0023 0.0024 0.0070 0.0048 0.0040 0.0027
System Loss Charge P/kWh 0.0268 0.0268 0.0268 0.0268 0.0268 0.0268
Gen. Rate SL VAT P/kWh 0.0265 0.0265 0.0265 0.0265 0.0265 0.0265
Trans. SL VAT P/kWh 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003
Distribution Revenues P/kWh 12% 12% 12% 12% 12% 12%
Others P/kWh 12% 12% 12% 12% 12% 12%
Universal Charge (PhP/kWh)
Missionary Electrification PhP/kWh 0.1561 0.1561 0.1561 0.1561 0.1561 0.1561
UCME - Subsidy 0.0454 0.0454 0.0454 0.0454 0.0454 0.0454
UCME - True-up Adj. for Cys 2003-2009 and for CY 2011 0.0709 0.0709 0.0709 0.0709 0.0709 0.0709
UCME - True-up Adjustment for CY 2010 0.0381 0.0381 0.0381 0.0381 0.0381 0.0381
UCME - RE Developer 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017
Environmental Charge PhP/kWh 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025
Stranded Contract Costs PhP/kWh 0.1938 0.1938 0.1938 0.1938 0.1938 0.1938
Average Rate PhP/kWh
Feed-in Tariff Allowance (FIT-ALL) PhP/kWh 0.1240 0.1240 0.1240 0.1240 0.1240 0.1240

 

Note:

1. Local Franchise Tax for Sultan Kudarat & Datu Odin Sinsuat Maguindanao Customers is 0.5%.

2. 12% VAT on distribution & other charges effective Feb. 1, 2006.

3. Fuel & Lubricant cost recovery of  Php0.0298/kwhr starting October, 2010 billing (ERC Case No. 2010-023 RC).

4. Universal Charge for Missionary Electrification  is PhP0.1163  starting Sept. 2011 billing.  ERC order under  ERC Case No. 2011-074 RC. NPC-SPUG Recovery of the shortfalls in the ME subsidy  for CY 2003 to 2009 under the True-up Mechanism pursuant to the Commission's Resolution No. 11. Series of 2005 is PhP0.0709/Kwh on top of the existing UC-ME of PhP0.0454/Kwh.

5. Universal Charge for Stranded Contract Costs of PhP0.1938/kWh starting April 2013 Billing. ERC Case No. 2011-091 RC docketed Feb. 19, 2013. RC docketed Oct. 14, 2013.

6. Universal Charge for Missionary Electrification RE Developer of PhP0.0017/kWh starting January 2014 Billing. ERC Case No. 2012-085

7. Feed-In-Tariff Allowance of PhP0.0406/kWh implemented starting Feb. 2015 billng in compliance with ERC Case No. 2014-019 RC.

8. Feed-In-Tariff Allowance increased from Php0.0406/kWh to Php0.1240/kWh effective April 2016 rate/billing in compliance with ERC Case No. 2015-216 RC Order dated. 2/16/16.